• Privacy policy
  • T&C’s
  • About Us
    • FAQ
    • Meet the Team
  • Contact us
TLE ONLINE SHOP!
  • TLE
  • News
  • Politics
  • Business
  • Sport
  • Opinion
  • Elevenses
  • Entertainment
    • All Entertainment
    • Film
    • Lifestyle
      • Horoscopes
    • Lottery Results
      • Lotto
      • Thunderball
      • Set For Life
      • EuroMillions
  • Food
    • All Food
    • Recipes
  • Property
  • Travel
  • Tech/Auto
  • JOBS
No Result
View All Result
The London Economic
SUPPORT THE LONDON ECONOMIC
NEWSLETTER
  • TLE
  • News
  • Politics
  • Business
  • Sport
  • Opinion
  • Elevenses
  • Entertainment
    • All Entertainment
    • Film
    • Lifestyle
      • Horoscopes
    • Lottery Results
      • Lotto
      • Thunderball
      • Set For Life
      • EuroMillions
  • Food
    • All Food
    • Recipes
  • Property
  • Travel
  • Tech/Auto
  • JOBS
No Result
View All Result
The London Economic
No Result
View All Result
Home News

MoD nuclear infrastructure upgrade £1.35bn over-budget

The National Audit Office says poor management has resulted in cost overruns and years of delays.

Joe Mellor by Joe Mellor
2020-01-10 13:56
in News
Photo: PA

Photo: PA

FacebookTwitterLinkedinEmailWhatsapp

Poor management of the infrastructure to build and maintain Britain’s Trident nuclear deterrent has led to years of delays and cost overruns of more than £1 billion, the Whitehall spending watchdog has warned.

The National Audit Office (NAO) said failure of the Ministry of Defence (MoD) to learn from past mistakes meant key projects to upgrade the Defence Nuclear Enterprise were over-budget and behind schedule.

It said “inappropriate” contracts with outside contractors and beginning building work on facilities before the designs were “sufficiently mature” had added hundreds of millions of pounds to costs.

And it highlighted a lack of technical skills within the MoD which resulted in the “gold-plating” of designs as staff were unable to challenge regulators when they insisted upon overly-complex specifications.

Nuclear
No 10 adviser Dominic Cummings will lead a review of defence spending (Kirsty O’Connor/PA)

The findings come as the Prime Minister’s chief adviser Dominic Cummings is preparing to launch a far-reaching review of defence spending amid long-standing concerns that billions are being squandered on botched procurements.

NAO

The NAO examined three programmes within the Nuclear Enterprise to replace ageing facilities, some dating back to the 1950s:

– Project Mensa to construct a new nuclear warhead assembly and disassembly facility at the Atomic Weapons Establishment site at Burghfield

RelatedPosts

Watch: ‘Moving to tears’ as EU flag brought into Ukranian Parliament ‘to stay’

Does Sue Perkins’ NSFW comment about ‘the government’ chime with you?

Watch: Turkish president scares PM but is it due to poem Johnson wrote about him?

Metropolitan Police officers sacked over ‘abhorrent and discriminatory’ messages

– The building of a new core production capability (CPC) at the Rolls Royce site at Raynesway to produce the latest nuclear reactor core designs

– The primary build facility at the BAE Systems shipyard at Barrow-in-Furness where the new Dreadnought class submarines to carry the Trident nuclear missiles will be built.

While the three projects were valued at £2.5 billion, the NAO found that costs had risen by £1.35 billion with delays running at between 1.7 and 6.3 years.

Nuclear
The Royal Navy nuclear submarine HMS Vanguard, (Royal Navy/PA)

The NAO said it was “disappointing” the MoD was continuing to repeat mistakes made in the last cycle of investment in the nuclear enterprise in the 1980s and 1990s.

They included “starting to build before requirements or designs were sufficiently mature, increasing risks through inappropriate contracts and failing to engage with regulators to understand requirements”.

UK civil nuclear projects

Similar problems had also been encountered in UK civil nuclear projects and US defence programmes, but the NAO said it had found no evidence of lessons being shared or learned.

Among the specific problems highlighted, the NAO said delays to project Mensa had meant the MoD having to spend an additional £21 million keeping existing facilities going.

It also pointed to the issue of “gold plating” of design specifications as both the MoD and the site operators struggled to recruit staff able to challenge complex demands by regulators.

“Throughout our study, the department, regulators and site operators all considered it had occurred and remained a potential risk,” it said.

Gareth Davies, the head of the NAO, said: “While these infrastructure projects are complex, the MoD has encountered similar challenges before in its nuclear work.

“Although it has recently introduced changes to enhance its oversight of the projects and improve its contracts with suppliers, it should have learnt earlier from past mistakes and the experience of others in the nuclear sector.

“Instead, the MoD’s failure to mitigate commercial and delivery risks early on has led to project delays and cost increases, as well as impacting its wider work.”

Related – Boris Johnson column from 2006 argues that the US should just “give the Iranians a nuclear bomb”

Since you are here

Since you are here, we wanted to ask for your help.

Journalism in Britain is under threat. The government is becoming increasingly authoritarian and our media is run by a handful of billionaires, most of whom reside overseas and all of them have strong political allegiances and financial motivations.

Our mission is to hold the powerful to account. It is vital that free media is allowed to exist to expose hypocrisy, corruption, wrongdoing and abuse of power. But we can't do it without you.

If you can afford to contribute a small donation to the site it will help us to continue our work in the best interests of the public. We only ask you to donate what you can afford, with an option to cancel your subscription at any point.

To donate or subscribe to The London Economic, click here.

The TLE shop is also now open, with all profits going to supporting our work.

The shop can be found here.

You can also SUBSCRIBE TO OUR NEWSLETTER .

Subscribe to our Newsletter

View our  Privacy Policy and Terms & Conditions

Trending on TLE

  • All
  • trending
Abdollah

‘Rescue us’: Afghan teacher begs UK to help him escape Taliban

CHOMSKY: “If Corbyn had been elected, Britain would be pursuing a much more sane course”

What If We Got Rid Of Prisons?

More from TLE

Johnson blimp takes to the skies in Manchester

Hairy Biker Dave Myers reveals he has cancer

Hotel Review: W Koh Samui, Thailand

Thunderball Results for Tuesday 2 November 2021 Tonight’s winning numbers

Turkey begins offensive against Kurdish fighters in Syria

Panic as earthquake ‘violently’ shakes homes across England

Ecofin Global Utilities and Infrastructure Trust – Compelling three-year track record

GB News recorded £3 million loss before botched launch

Collabo Review: Hip-Hop With a Difference

Boris Johnson running scared of tonight’s TV election debate on climate change

JOBS

FIND MORE JOBS

About Us

TheLondonEconomic.com – Open, accessible and accountable news, sport, culture and lifestyle.

Read more

© 2019 thelondoneconomic.com - TLE, International House, 24 Holborn Viaduct, London EC1A 2BN. All Rights Reserved.




No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
  • Entertainment
  • Lifestyle
  • Food
  • Travel
  • JOBS
  • More…
    • Elevenses
    • Opinion
    • Property
    • Tech & Auto
  • About Us
    • Meet the Team
    • Privacy policy
  • Contact us

© 2019 thelondoneconomic.com - TLE, International House, 24 Holborn Viaduct, London EC1A 2BN. All Rights Reserved.